Phase F: Migration Planning Knowledge-Based Practice

TOGAF · Enterprise Architecture Capability and Governance · Foundation · Establishing an Architecture Capability

3 Foundation practice questions on Phase F: Migration Planning. Questions that assess core concepts and understanding.

Layout:

Choose how questions appear in the preview and test.

Preview the questions below, then start to answer and see your results.

Questions

  1. 1.

    In the TOGAF Architecture Development Method (ADM), which main activity distinguishes Phase F (Migration Planning) from Phase E (Opportunities and Solutions)?

    • A) Finalizing the detailed Implementation and Migration Plan in co-operation with portfolio and project managers.
    • B) Identifying candidate work packages and constructing the initial version of the Architecture Roadmap.
    • C) Formulating the Architecture Vision and obtaining approval for the Statement of Architecture Work.
    • D) Establishing the Architecture Capability and defining the enterprise-specific tailored ADM.
  2. 2.

    Which activity is a primary responsibility carried out during Phase F (Migration Planning) of the TOGAF ADM?

    • A) Prioritizing implementation projects through cost/benefit assessments and risk analysis to finalize the Implementation and Migration Plan.
    • B) Defining baseline business architecture and selecting target business architecture building blocks.
    • C) Establishing the initial Architecture Vision and securing approval for the Statement of Architecture Work.
    • D) Monitoring the implementation of governance frameworks and conducting architecture contract compliance reviews.
  3. 3.

    What is a key objective of Phase F (Migration Planning) in the TOGAF Architecture Development Method (ADM)?

    • A) To finalize the Implementation and Migration Plan and align it with the enterprise's portfolio and project management frameworks.
    • B) To create the initial draft of the Architecture Roadmap and outline candidate work packages.
    • C) To provide ongoing architectural oversight to ensure implementation projects comply with the Target Architecture.
    • D) To establish the Architecture Vision and obtain formal approval to initiate an architecture cycle.

Answers and step-by-step solutions appear after you finish the test.